Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page.
*This report is submitted from ICS on a weekly basis.
Sheridan Hills Elementary
Completed week ending Friday, October 1, 2021
- Contractors continued addressing punchlist items.
- Continued testing and balancing of the HVAC/mechanical systems.
- IEA to resume commissioning of the HVAC/mechanical systems.
Planned week ending Friday, October 8, 2021
- Contractors to continue addressing punchlist items.
- Continue testing and balancing of the HVAC/mechanical systems.
- IEA continued commissioning of the HVAC/mechanical systems.
Richfield Middle School
Completed week ending Friday, October 1, 2021
- Doors delivered for Best Buy Teen Tech Center
- Reinstalled ceilings in auditorium space
- Flushed and cleaned hydronic system for auditorium space
- Patched, repaired, and painted canopy face where signage was removed
- Conducted training on sprinkler system
- Boiler Room punch list
Planned week ending Friday, October 8, 2021
- Install doors in Best Buy Teen Tech Center
- Conduct training and state inspections on water heaters, and pumps in boiler room
- Exhaust modifications and turnover loading dock bathrooms
Central Education Center
Completed week ending Friday, October 1, 2021
- Contractors continued addressing punchlist items.
- Continued plumbing and hydronic piping and insulation in the lower-level mechanical spaces.
- Conducted chiller unit start-up and Owner training.
Planned week ending Friday, October 8, 2021
- Install new interior room signage.
- Continue plumbing and hydronic piping and insulation in the lower-level mechanical spaces.
- Contractors to continue addressing punchlist items.
- All-State tentatively scheduled to conduct Owner training on visitor management system with building staff and facilities.