Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Richfield High School

Completed week ending Friday, November 13, 2020

  • Boiler Room
    • Insulation of piping
  • Area C 3rd level science rooms
    • Final cleaned and ready for turnover
  • Area C 3rd level restrooms
    • Final cleaned and ready for turnover
  • New Athletic Corridor/Elevator
    • Elevator phone hook up
    • Fin tube radiation installation
  • Main Gym
    • Installed volleyball sleeves for auxiliary courts

Planned week ending Friday, November 20, 2020

  • Boiler Room
    • Commissioning, testing and balancing
  • Area P Link
    • Waiting for windows and storefront door delivery
  • Lower Level Area F Dance Studio/Weight Room/Wrestling
    • Interior glass installation, and waiting for wall pad delivery
  • New Athletic Corridor/Elevator
    • Elevator inspection and turnover

Centennial Elementary

Completed week ending Friday, November 13, 2020

  • Contractors continued working to address punch list and IEA Commissioning log items.
  • IEA Commissioning to continue commissioning of the mechanical/HVAC systems.

Planned week ending Friday, November 20, 2020

  • Contractors to continue working to address punch list and IEA Commissioning log items.
  • IEA Commissioning to continue commissioning the mechanical/HVAC systems.

Sheridan Hills Elementary

Completed week ending Friday, November 13, 2020

  • Contractors continued working to address punch list and IEA Commissioning log items.
  • IEA Commissioning continued the commissioning of the mechanical/HVAC systems.
  • Continued chiller system piping installation in the Lower Level mechanical spaces.
  • Started above grade CMU walls on the Kitchen/Receiving area addition.

Planned week ending Friday, November 20, 2020

  • Contractors to continue to address punch list and IEA Commissioning log items.
  • IEA Commissioning to continue commissioning the mechanical/HVAC systems.
  • Complete above grade CMU at the chiller enclosure.
  • Continue Lower Level mechanical piping and boiler installation.

Richfield Middle School

Completed week ending Friday, November 13, 2020

  • Phase 2 Area D Special Education/Link
    • Installed acoustical ceiling pads throughout
  • Phase 2 New Conference Room and Staff Lounge
    • Installed acoustical ceiling pads
  • Phase 2 FACS Lab
    • Tape, mud, and sand walls
    • Painted walls
  • Phase 2 Chiller Tower
    • Chiller piping continued
  • Phase 3 Third Floor Restrooms
    • Installed gyp board ceiling in north restrooms
    • Installed toilet partitions in north restrooms
    • Started tiling in south restrooms

Planned week ending Friday, November 20, 2020

  • Phase 2 Area D Special Education/Link
    • Restroom partitions and toilet accessory installation
    • Wall covering in classrooms
  • Phase 2 New Conference Room and Staff Lounge
    • Waiting for casework delivery
  • Phase 2 FACS Lab
    • Install ceiling grid
  • Phase 2 Chiller Tower
    • Continue chiller piping
  • Phase 3 Third Floor Restrooms
    • Install grab bars and accessories in north restrooms
    • Finish tiling in south restrooms

Richfield STEM Elementary

Completed week ending Friday, November 13, 2020

  • Continued testing, balancing, and commissioning of mechanical systems

Planned week ending Friday, November 20, 2020

  • Continue testing, balancing, and commissioning of mechanical systems

Richfield Dual Language School

Completed week ending Friday, November 13, 2020

  • Contractors continued working to address items noted on the commissioning corrective action log.
  • Contractors worked to address issues identified during the 11-month warranty walkthrough.

Planned week ending Friday, November 20, 2020

  • Contractors to continue working to address items noted on the commissioning corrective action log.
  • Contractors to continue working to address issues identified during the 11-month warranty walkthrough.