Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page.
*This report is submitted from ICS on a weekly basis.
Richfield High School
Completed week ending Friday, January 15, 2021
- Wall pads in wrestling room shipped and in transit
- Cleared out construction materials and cleared out auxiliary gyms
- Continued punch list item completion
- Continued testing, balancing, and commissioning
- Scheduled 11-month warranty walk through for Phase 3 areas
Planned week ending Friday, January 22, 2021
- Receive and begin installation of wrestling room wall pads
- Continue punch list items
- Continue testing, balancing, and commissioning
Centennial Elementary
Completed week ending Friday, January 15, 2021
- All punch list items are now complete except for (3) items that will be completed in the spring when warmer weather arrives
- IEA Commissioning to continue commissioning the mechanical/HVAC systems
- Contractors continued working IEA Commissioning log items
- Utility rebate applications have been submitted
Planned week ending Friday, January 22, 2021
- Contractors to continue working to address IEA Commissioning log items
- IEA Commissioning to continue commissioning the mechanical/HVAC systems
Sheridan Hills Elementary
Completed week ending Friday, January 15, 2021
- Completed hydronic piping runs to the new chiller
- IEA Commissioning continued the commissioning of the mechanical/HVAC systems
- Contractors continued working to address punch list and IEA Commissioning log items
- Utility rebate applications have been submitted
Planned week ending January 22, 2021
- Contractors to continue to address punch list and IEA Commissioning log items
- IEA Commissioning to continue commissioning the mechanical/HVAC systems
- Continue installing hydronic piping runs to the new chiller unit and making final connections.
Richfield Middle School
Completed week ending Friday, January 15, 2021
- Phase 2 New Conference Room and Staff Lounge
- Turned over to school
- Phase 2 FACS Lab
- Punch list items (countertops)
- Phase 3 Third Floor Restrooms
- Finish toilet partitions
- Phase 3 Second Floor Restrooms
- Sheetrocked in south restroom
- Started installing plumbing fixtures in north restroom
- Phase 3 Existing Administration Offices
- Mechanical, electrical, plumbing rough ins
- Finished wall framing
- Wood backing installed in walls
- Phase 3 Existing Music Suite
- Poured in concrete floors at tiered areas in Band Room
- Started mechanical and electrical rough ins
- Prep work to infill Choir Room tiered floor
- Start demolishing ceilings
- Wood Shop
- Equipment and furniture cleared out in preparation for demolition
- Abatement bids for next phase received
Planned week ending Friday, January 22, 2021
- Phase 3 Third Floor Restrooms
- Finish ceiling
- Phase 3 Second Floor Restrooms
- Tile work in south restroom
- Above ceiling mechanical work in south restroom
- Toilet partitions in the north restrooms
- Phase 3 Existing Administration Offices
- Finish in wall mechanical and electrical rough ins
- Finish wood backing
- Start sheet rocking walls
- Phase 3 Existing Music Suite
- Finish demolition of ceilings
- Continue mechanical and electrical rough ins
Richfield STEM Elementary
Completed week ending Friday, January 15, 2021
- Continued testing, balancing, and commissioning
- All State to come on site to resolve minor punch list items
Planned week ending Friday, January 22, 2021
- Continue testing, balancing, and commissioning
- Get proposals for non-construction contract scope items (electrical work, light fixtures, soffit repairs in stairwells)
Richfield Dual Language School
Completed week ending Friday, January 15, 2021
- Contractors continued working to address items noted on the commissioning corrective action log
Planned week ending Friday, January 22, 2021
- Contractors to continue working to address items noted on the commissioning corrective action log
Central Education Center
Completed week ending January 15, 2021.
- Continued preconstruction work with Rochon
- Rochon completed and submitted the building permit application to the City of Richfield
- ICS and District personnel held a coordination meeting with All Furniture (the moving company) to review the site in preparation of the upcoming packing and moving
- ICS presented the packing and moving plan to the building staff on 1/13
- Scheduled the preconstruction meeting for 1/22
- IEA (the abatement scope consultant) conducted a walkthrough of the building with contractors who plan to provide quotes for the abatement scope
Planned week ending Friday, January 22, 2021
- Continue preconstruction work with Rochon and moving coordination with the District
- Hold the Preconstruction meeting with ICS, Wold, Rochon and District Staff
- IEA to receive quotes for the abatement scope