ICS Weekly Report: October 8, 2021

Decorative image with colored diamonds on gray background

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Sheridan Hills Elementary

Completed week ending Friday, October 8, 2021

  • Contractors continued addressing punch list items.
  • Continued testing and balancing of the HVAC/mechanical systems.
  • IEA resumed commissioning of the HVAC/mechanical systems.
  • Started earthwork for the egress pathway from the Cafeteria to the City sidewalk.

Planned week ending Friday, October 15, 2021

  • Contractors to continue addressing punch list items.
  • Continue testing and balancing of the HVAC/mechanical systems.
  • IEA to continue commissioning of the HVAC/mechanical systems.
  • Complete asphalt paving at egress path.

Richfield Middle School

Completed week ending Friday, October 8, 2021

  • Installed doors in Best Buy Teen Tech Center
  • Conducted training and state inspections on water heaters, and pumps in boiler room
  • Exhaust modifications and turned over loading dock bathrooms

Planned week ending Friday, October 15, 2021

  • Punch list and commissioning

Central Education Center

Completed week ending Friday, October 8, 2021

  • Contractors continued addressing punch list items.
  • Continued plumbing and hydronic piping and insulation in the lower-level mechanical spaces.
  • Continue plumbing and hydronic piping and insulation in the lower-level mechanical spaces.

Planned week ending Friday, October 15, 2021

  • Contractors to continue addressing punch list items.
  • Continue hydronic piping and insulation in the lower-level mechanical spaces.
  • Boiler system start-up scheduled for October 11th.

Download the PDF Report